Bergisel Paves the Way for the Future
On Tuesday morning, a helicopter was in action at the Olympic ski jump in Innsbruck to fly in the masts for the new floodlight system.
The Bergisel ski jump in Innsbruck is getting ready for night competitions.
On Tuesday morning, a cargo helicopter flew in the masts for the new floodlight system at the Olympic ski jump. A total of seven masts, up to 31 meters high, were delivered with the first shipment. The largest parts weigh up to seven tons. The entire system was installed on the east side of the ski jumping stadium.
"During planning, we placed particular emphasis on ensuring that the floodlights blend harmoniously into the overall picture. We didn't clear any trees either," Bergisel Managing Director Bernhard Niggler is quoted by "Krone". For the mast behind the Olympic flame, a mobile version is being used so as not to permanently obstruct the view of the city.
Total Costs Lower Than Estimated
Official acceptance will take place on December 20, before things get serious at the Four Hills Tournament on January 2 and 3, 2027. "The joy is incredibly great. We fought for these floodlights for a long time; they are important for the flexibility of start times. Previously, one had to abort in the dark," emphasizes ÖSV Sports Director Mario Stecher to "Krone".
Now all venues of the Four Hills Tournament also have a floodlight system. "Without this investment, the women's competition would not have been possible in time," admits Stecher, who describes the women's premiere as a "highlight for the 75th anniversary."
As "Krone" reports, the total costs are below the estimated 4.8 million Euros. The federal government and the state each bear one third of the investments, with the remaining third shared by the city of Innsbruck and Ski Austria. Operating costs are estimated at around 78,000 Euros per year.